.If A takes 6 days to complete a work and B takes 8 days to complete the same work, then how days it takes if they work together? i did like 1/6+1/8=7/24 so my answer is 3.7 is it correct
Follow Math Help Forum on Facebook and Google+
they complete 7/24 of the work in one day, yes. so they take 24/7 days to complete it. 3.42 days. not 3.7