Not too sure where to post this but its a basic math problem:
Shift Hours: 8:00-15:30
Number of man hours to complete a car: 12hr
Total Workers per day: 117
Target cars per day: 80
If the target for cars produced per day where to increase to 100 without increasing the number of staff, what time roughly would be daily shift end (assume normal start 8:00) to meet this target?
The ans is either 16:45, 17:30, 18:15, 19:00 or 19:45
Many Thanks for you help!