Determine the probability of completing this project in time for the product launch in 34 weeks.
The critical path is 33.5 weeks with a standard deviation of .56203.
A little lost on this, and guidance would be appreciated.
This is what I have done so far. I am struggling with the remainder of A4. Determine the probability of completing this project in time for the product launch in
34 weeks.I have added the work I have completed so far. If you could point me in the right direction that would help.