    Probability of completion.

    Determine the probability of completing this project in time for the product launch in 34 weeks.

    The critical path is 33.5 weeks with a standard deviation of .56203.

    A little lost on this, and guidance would be appreciated.
    Follow Math Help Forum on Facebook and Google+

  2. #2
    Flow Master
    mr fantastic's Avatar
    Joined
    Dec 2007
    From
    Zeitgeist
    Posts
    16,948
    Thanks
    5
    Quote Originally Posted by ThanksinAdvance View Post
    Determine the probability of completing this project in time for the product launch in 34 weeks.

    The critical path is 33.5 weeks with a standard deviation of .56203.

    A little lost on this, and guidance would be appreciated.
    Have you posted all of the question? Are you familiar with critical path analysis?
    Follow Math Help Forum on Facebook and Google+

  3. #3
    MHF Contributor matheagle's Avatar
    Joined
    Feb 2009
    Posts
    2,763
    Thanks
    5
    do we have normality here?
    Follow Math Help Forum on Facebook and Google+

  4. #4
    Flow Master
    mr fantastic's Avatar
    Joined
    Dec 2007
    From
    Zeitgeist
    Posts
    16,948
    Thanks
    5
    Quote Originally Posted by matheagle View Post
    do we have normality here?
    There beta be ....
    Follow Math Help Forum on Facebook and Google+

  5. #5
    Newbie
    Joined
    Dec 2010
    Posts
    10
    Quote Originally Posted by mr fantastic View Post
    Have you posted all of the question? Are you familiar with critical path analysis?
    This is what I have done so far. I am struggling with the remainder of A4. Determine the probability of completing this project in time for the product launch in
    34 weeks.
    I have added the work I have completed so far. If you could point me in the right direction that would help.

    Thanks,
    Attached Files Attached Files
    Last edited by ThanksinAdvance; January 3rd 2011 at 07:06 PM. Reason: Added attachment.
    Follow Math Help Forum on Facebook and Google+

Similar Math Help Forum Discussions

  1. completion of space
    Posted in the Differential Geometry Forum
    Replies: 1
    Last Post: February 20th 2011, 10:10 AM
  2. Completion of the Hyperreal numbers?
    Posted in the Differential Geometry Forum
    Replies: 0
    Last Post: February 19th 2011, 04:09 AM
  3. completion of set in metrix spaces
    Posted in the Differential Geometry Forum
    Replies: 5
    Last Post: December 1st 2010, 02:31 PM
  4. Replies: 1
    Last Post: February 18th 2010, 01:54 AM
  5. directed acyclic graph completion time distribution
    Posted in the Differential Geometry Forum
    Replies: 0
    Last Post: August 14th 2009, 11:28 PM

Search Tags


/mathhelpforum @mathhelpforum